Selections and finish schedules

A remodel is several hundred decisions, and the ones that cause trouble are never the difficult ones. They are the small ones nobody wrote down.

Planning · 7 min read · Written & reviewed by Jan Revels, ASID · designing in Dallas since 1997

Short answer

Decide in order of constraint. The things with the fewest options come first — stone slabs, appliances, cabinetry — and paint comes last, because paint can be mixed to match anything and nothing can be mixed to match paint.

Write everything into one finish schedule: room, element, product, manufacturer, model, color, finish, size, quantity, supplier and status. One document, one version, shared with everyone.

Every open decision at the start of construction becomes a change order later. Closing decisions early is the cheapest budget control available.

What order should selections be made in?

The principle is simple and it settles nearly every argument: decide the constrained things first, the flexible things last. A slab of quartzite comes in the colors it comes in; paint comes in every color that exists.

  1. Appliances — fixed dimensions, and cabinetry is built around them. See kitchen appliance planning.
  2. Plumbing fixtures — their specifications drive rough-in positions.
  3. Cabinetry — style, finish and layout, which sets the room’s architecture.
  4. Stone and countertops — the least flexible material in the house. Chosen from what physically exists.
  5. Flooring — large area, limited palette, and it runs through several rooms.
  6. Tile — chosen against the stone, which is why it comes after.
  7. Lighting — positions before drywall, fixtures later.
  8. Hardware and plumbing finishes — the metal thread that ties the rooms together.
  9. Paint — last, always. Matched to everything already chosen. See choosing paint colors.

Two decisions cut across this list and are worth making at the very start: the metal finish and the wood tone. Both appear in every room, and both are far easier to hold consistent if named on day one.

What does a finish schedule contain?

ColumnWhy it is there
RoomEverything is located; nothing is “the bathroom” when there are three
ElementFloor, wall tile, vanity top, faucet, pull, paint
Manufacturer and modelThe only unambiguous identifier
Color / finishIncluding the exact finish code, not just “brass”
Size and quantityWith overage stated for tile and flooring
SupplierWho it comes from, and who is ordering it
Lead timeSo the schedule can be built around it
StatusSelected, approved, ordered, received, installed
NotesGrout color, edge profile, mounting height, orientation

The notes column earns its place. “Grout: mid-gray, epoxy”, “Edge: mitered 3cm”, “Sconce center at 62 inches” — these are the details asked on site at eight in the morning, and if they are not written down somebody guesses.

One document, one version

A written finish schedule is what stops the same question being asked three times and answered differently — and it is what a trade needs at seven in the morning when nobody is answering the phone.

Jan Revels produces the schedule, keeps it current and issues it to the trades.

Working with samples properly

Deadlines, and what happens when one slips

Each selection has a moment after which it is expensive:

SelectionMust be settled by
AppliancesBefore cabinetry is drawn
Plumbing fixturesBefore rough-in
Shower valve and body spraysBefore rough-in — these are inside the wall
Blocking locationsBefore drywall
Switch and outlet positionsBefore drywall
Tile and setting-outBefore the tiler starts
Cabinetry finishBefore fabrication
StoneBefore templating, which is after cabinets are set
PaintLate — but before the painter is booked

When a deadline slips, the cost is rarely the item. It is the trade who was booked, moved to another job, and is now unavailable for three weeks. That is why unmade decisions are the largest single cause of delay — see what a remodel timeline really looks like.

When you cannot decide

Recording it for later

When the project ends, keep a closeout file. In five years you will want:

Key takeaways

  • Decide in order of constraint. Stone and appliances early, paint last, always.
  • Name the metal finish and the wood tone on day one; they appear in every room.
  • One finish schedule, one version, with a notes column for grout, edges and heights.
  • Judge samples together, in the room, at three times of day.
  • Shower valves and blocking are inside walls — decide before rough-in and drywall.
  • A slipped decision costs the trade’s availability, not the item.
  • Keep a closeout file: paint colors, offcuts, models, warranties and photographs.

Frequently asked questions

What order should I make selections in?
In order of how constrained each choice is. Appliances first, because cabinetry is built around their fixed dimensions; then plumbing fixtures, whose specifications drive rough-in; then cabinetry, stone, flooring, tile, lighting, hardware, and paint last of all. Paint can be mixed to match anything, and nothing can be mixed to match paint — which is why choosing it early is the most common sequencing mistake.
What is a finish schedule?
A single document listing every selection by room and element, with manufacturer, model, color and finish code, size, quantity with overage, supplier, lead time, status and notes. The notes column carries the details asked on site early in the morning — grout color, edge profile, mounting heights. Without it, the same question gets asked three times and answered differently.
How do I judge samples properly?
In the actual room rather than the showroom, and all together rather than one at a time — cabinet door, stone, tile, floor and hardware held in one hand. Look at them at three times of day and once under artificial light. Get samples large enough to be meaningful, particularly for stone with movement, and photograph the approved combination with a date so deliveries can be checked against it.
What happens if I am late making a decision?
The cost is rarely the item itself — it is the trade who was booked for that week, moved to another job, and is now unavailable for three weeks. Unmade decisions are the single largest cause of delay on a remodel, and they are the one cause entirely within your control. The critical deadlines are before cabinetry is drawn, before rough-in, and before drywall.
What should I keep after the project finishes?
Paint colors by room with sheens, and the leftover tins labeled; tile and stone details plus a box of offcuts for repairs; appliance models, serial numbers and warranties; plumbing fixture models for replacement cartridges; the cabinetmaker, door style, finish and hardware so future work can match; photographs taken before the walls were closed; and the permits, inspection records and trade contacts.
Jan Revels, ASID Allied Professional Interior Designer
ASID Allied Professional Interior Designer · Chateau Concepts, Dallas

Jan has practiced interior design in Dallas since 1997 and founded Chateau Concepts in 2001. She holds a BFA in Interior Design from the University of North Texas. She designs and general-contracts residential and commercial projects across the Park Cities, Preston Hollow and North Dallas. Read her full profile →

Written and reviewed by Jan Revels before publication

Drowning in samples?

The problem is almost always sequence rather than volume. Get the order right and the choices narrow themselves.