Kitchen and wet bar remodel in University Park: who designs and builds both?

Where the bar goes in a University Park house, wet or dry on a slab, the sizes that work, one appliance schedule and one cabinet order for both rooms, the town’s permit meeting and a realistic timeline.

Remodeling · 13 min read · Written & reviewed by Jan Revels, ASID Allied, American Society of Interior Designers · designing in Dallas since 1997
Published

Short answer

Hire one team to design and build both so the kitchen and bar share one set of drawings, one appliance schedule, one cabinetry order, and one plumbing rough-in. Chateau Concepts does this in University Park, Texas. Jan Revels, ASID Allied, draws both spaces to scale, makes selections with you, and runs construction herself as the general contractor.

Key takeaways

Who should be responsible for both rooms?

Ask who will draw the floor plan and elevations, who will order the cabinets, and who will make the field decision if an opened wall reveals an unexpected pipe. At Chateau Concepts, Jan handles the design and acts as the general contractor. She can look at the condition on site, see what it affects in both rooms, and check the work against the approved drawings.

Jan has practiced interior design in Dallas since 1997 and founded Chateau Concepts, LLC in 2001. She holds a BFA in Interior Design from the University of North Texas and is an ASID Allied member. If you are looking for an interior designer in University Park, ask to see how the floor plan carries through to the cabinet elevations. The plan tells you where the bar goes. The elevations show what fits along the wall, where the appliances sit, and how the cabinets meet the opening or trim.

Chateau Concepts, LLC is registered with the City of Dallas as a general contractor and carries general liability insurance. Certificates are available on request. University Park has its own building department and permit process. When we handle general contracting, Jan schedules trades, orders and tracks materials, manages permits, walks the site, and checks the installation against the drawings you approved.

Where should the bar go in your University Park house?

University Park grew alongside Southern Methodist University from the 1920s onward. Its housing ranges from period cottages and revival houses to newer rebuilds on original lots. In an older house with defined rooms, the feeling that the kitchen is cut off often comes down to the wall to the breakfast room. That wall is often structural, so we establish what it carries and locate the plumbing stack and gas line before drawing a new layout.

Where the bar can go in a University Park house

PositionWorks whenWatch for
Breakfast room wallThe wall offers a place to serve drinks or coffee outside the cook’s path.Appliance doors, guests, and pulled-out chairs can compete for the same floor space.
Butler’s pantryThe pantry is on the route to the dining room and has room for beverage service and glassware.A narrow passage can get crowded when someone opens a refrigerator door or stops to pour.
Family or dining room openingGuests can approach from the adjoining room while the kitchen stays open for cooking.Check the structure, the clear opening, and how the cabinet run ends at the trim or arch.

What this means for you: Walk from the family or dining room to each proposed bar location while someone else stands at the sink or range. Then picture the appliance door open and someone waiting for a drink. That exercise usually tells us more about the placement than an empty room does.

At a breakfast room wall, we look at the table and seating before filling the wall with cabinets. A short beverage station near the end of the kitchen run may serve breakfast and parties while leaving the table easy to reach. If the remodel also includes a banquette or a wider opening, we draw those changes with the bar so the cabinet depth and seating work together. See what can be planned together in a kitchen and breakfast room remodel.

A butler’s pantry works especially well when you carry plates into the dining room and want drinks and glassware on that same route. We draw out which stretch of counter stays open for setting down a tray and where someone can stop to make a drink. If the pantry also handles food prep or cleanup, those uses need their own working space. We consider them together in butler’s pantry and scullery design.

An opening to the family or dining room can put the bar right where guests enter. On one Chateau Concepts project, we kept the arch and rebuilt the plain wall beneath it as a wet bar with a granite counter, glass-front cabinets, and a mosaic tile surround. If your plan calls for widening an opening, establish what the wall supports before removing a load-bearing wall.

Wet bar built under an arched opening, with a granite counter, glass-front cabinets and a mosaic tile surround
A Chateau Concepts wet bar, after: a plain wall under an arched opening was rebuilt as a bar with a granite counter, glass-front cabinets and a mosaic tile surround. The arch was kept as its frame, so the bar reads as part of the house rather than an add-on.

Is a wet bar worth adding if your house is on a slab?

We plan the bar in this order: position, plumbing, then cabinetry. A bar sink needs a water supply, a drain, and a vent. On a slab, a new drain usually means cutting concrete. A post-tension slab also requires care around the tensioning cables, so the route needs to be understood before you commit to the sink location.

Wet bar or dry bar

OptionWhat you getWhat drives the decision
Wet barA sink for rinsing glasses and emptying drinks where you serve them.A viable supply, drain, and vent route. A new drain on a slab usually means cutting concrete.
Dry barA place to pour, store glasses, and chill drinks, with the kitchen sink available nearby.Distance to the kitchen sink and the power and plumbing needs of the appliances you choose.

What this means for you: If the bar is within about twenty feet of the kitchen sink, a beverage refrigerator and ice service can give you nearly all the function you need. In a farther room, a sink earns its place because you can rinse and empty glasses where you use them.

Screenshot of the Chateau Concepts wet bar versus dry bar comparison table, with the row on a slab foundation outlined in orange
From our guide Wet bars and beverage stations. Look at the outlined row: on a slab foundation a wet bar usually means cutting concrete for the drain, a dry bar needs no concrete work. That one line decides most University Park bars. Screenshot: chateauconcepts.com, November 2026.

Decide how you want to make ice before you settle on a dry bar. A plumbed ice maker needs both a water supply and a drain, even if the bar has no sink. If you want to avoid a new drain, confirm the ice maker’s requirements early enough to choose a different setup. When you do add a sink, a 15-inch bar sink is enough for typical use, and a deeper bowl is more useful for rinsing than a wider one.

Consider the kitchen’s utility moves at the same time. Keeping the sink, range, and refrigerator in place helps avoid relocating plumbing and gas, the largest single cost variable in the remodel. If your kitchen already works, refreshing cabinetry, counters, tile, and lighting while putting the bar near existing plumbing is often the better value. Our guide to wet bars and beverage stations shows how the bar can serve the room around it.

How much wall space and clearance does the bar need?

A useful bar fits on about four to six feet of wall. With three feet, we plan a beverage station and give priority to the appliance you use most, a place to set down a glass, and storage for what you reach for there. A wider run gives you room to separate pouring, rinsing, and coffee service where the household uses all three.

Bar dimensions to check on the plan

FeatureDimension
Counter run36 inches minimum, 48 to 72 inches comfortable
Counter depth18 inches minimum, 24 to 25 inches for prep
Counter height36 inches, or 42 inches for a raised bar top
Clear floor in front36 inches, or 42 inches where guests gather
Upper cabinet clearance above the counter15 inches minimum, 18 inches comfortable
Seating12-inch overhang, or 15 inches with 24 inches of width per stool
Stemware shelf height11 to 12 inches

What this means for you: Measure usable wall space and clear floor space together. A bar can fit between the trim and still put an open refrigerator door in the dining route. Check the proposed cabinet depth with the appliance doors, seating, and nearby room doors drawn in place.

Bring the glasses, coffee gear, or bottles that you use most often into the design conversation. Stemware needs enough shelf height to lift a glass out easily. A coffee machine needs room to use it and reach its power, while a wine unit needs an opening that suits the model. We work out those details on the elevations before releasing custom built-ins and cabinetry for production.

The bar can take a darker cabinet color, contrasting wood, or stone with more movement than the kitchen counters. Because the surface is small, you can use a dramatic stone over a limited area. The Lighted Wet Bar in our portfolio uses lit glass-front cabinets above a stone counter, a strip light across the tile backsplash, and a glass-door wine refrigerator below.

Wet bar with a lighted glass-front cabinet, black counter and bar stools
Lighted Wet Bar, a Chateau Concepts project: lit glass-front cabinets over a stone counter and a glass-door wine refrigerator below. The shelf lighting runs inside the cabinets, which is why it is specified before the cabinet order goes in.

How do the kitchen and bar share one appliance schedule and cabinetry order?

We decide the layout first, then develop the cabinetry. Next come appliances and plumbing, then counters, backsplash, lighting, and hardware. Developing the cabinet layout establishes where everything belongs. Releasing the cabinet order comes after the appliance specifications are settled, because the actual models determine the openings.

  1. Choose the appliances for both rooms together. Put the beverage refrigerator, wine unit, and ice maker you plan to use on the same schedule as the kitchen appliances. Record the model, opening dimensions, ventilation needs, and utility connections. This is where kitchen appliance planning affects the bar as much as the kitchen.
  2. Match the drawings to the schedule. Check each opening against the appliance specifications and check door swing against adjacent cabinets and the walking route. Undercounter appliances should vent at the front, with the vent kept clear. A sealed cabinet cavity traps heat.
  3. Set the rough-in locations. Plan the bar’s supply, drain, and vent with the kitchen plumbing so the work can share one rough-in. Coordinate power before cabinets are made, including outlets in the backsplash area and the wiring for cabinet lighting. Two or three undercounter appliances plus a coffee machine may call for a dedicated circuit.
  4. Approve the elevations and release one cabinetry order. Check which finishes carry from the kitchen to the bar and where you want a deliberate change. Ordering together gives the cabinetmaker the full set of dimensions and finish choices while the trades can plan their work for both spaces in the same visit.

We look at the actual counter slab in daylight, then choose the backsplash standing beside it. Under cabinet lighting, tile and stone may read differently than they do as separate samples. For lighting, we plan task, ambient, and accent layers with separate switching and dimming. A concealed warm, dimmable strip works well with glass shelves, and we specify it before cabinet production because the wiring runs inside the cabinetry.

What does University Park require before work can start?

University Park is a separate municipality from Dallas and Highland Park. Its Community Development Department reviews residential building requests, and the city has its own requirements and inspections. New plumbing normally requires a permit. Plug-in appliances on an existing circuit may require no electrical work, while adding a dedicated circuit changes the scope. We check the requirements for the work shown on the drawings.

Since January 1, 2025, every University Park building permit application goes through a mandatory completeness meeting with the Building Permit Office. The city uses the meeting to determine whether the submission has enough information for formal review. A complete application enters the plan review queue. An application with missing information is rejected at that stage. The city’s Residential Plan Submittal Packet applies to remodels and additions.

Screenshot of the City of University Park building permits page describing the application process
The City of University Park building permits page: since January 1, 2025 every application goes through a completeness meeting before plan review. A kitchen and bar drawn as one complete set goes through once. Screenshot: uptexas.org, November 2026.

When Chateau Concepts is the general contractor, we file the applications and show you the approved permit. Standard job-site hours are 7 am to 6 pm, Monday through Saturday. Discuss school mornings and Saturday routines when we plan site access. For more on planning work in the city, see the University Park remodeling guide.

How long will the remodel take, and should you aim for summer?

Work backward from when you need the kitchen functioning again. Finish selections and approve cabinetry with lead time in mind, and allow for city review as you plan the construction start. Plan to be without a working kitchen during construction. Before the kitchen comes out, decide where you’ll keep everyday dishes and how you’ll handle meals and school lunches.

Typical kitchen and bar project timeline

PhaseTypical durationWhat controls the start
Design and selections6–12 weeksThe in-home consultation and agreement on scope
Cabinetry lead time6–16 weeks from approvalApproval of stock, semi-custom, or custom cabinetry
Custom millwork production, where specified10–16 weeksApproved millwork details
On-site construction6–12 weeksPermit approval and coordination of trades and materials
Counter template to installation2–4 weeksCabinets must be installed before templating

What this means for you: The table gives you planning ranges for individual phases. Counter fabrication follows cabinet installation and happens within the construction sequence. Custom millwork is a production lead time to account for when you choose cabinetry, so check how it fits into your order before setting a start date.

Summer is the obvious and busiest window. A summer-only remodel needs a genuinely small scope and every selection closed before work begins. A cabinet and finish refresh with a simple beverage station is easier to fit around a school break when the layout and utility locations already work. A wall opening, new slab plumbing, and custom cabinetry give a larger project more dependencies, so a fall start usually leaves more room to sequence the work.

If you’re weighing a summer refresh against a larger fall remodel, call 214-797-4657 or book a design consultation. At the house, we can talk through the layout, what the bar needs to do, and which decisions drive the start date.

How does Jan run the project from the first visit through construction?

  1. Walk the house with us. We ask how you cook, where people gather, and what you want the bar to handle. We look at the likely appliance locations, traffic paths, and existing utilities. Jan gives you her first impressions, including what the house can accommodate and where the plan faces a constraint.
  2. Review the floor plan and elevations to scale. Jan draws the kitchen and bar together so you can see how the work areas, appliances, and built-ins fit. This is the time to move a cabinet or reconsider the sink. Changes on paper cost nothing compared with moving work that is already installed.
  3. Make selections together. We work through cabinetry, appliances and plumbing, counters, backsplash, lighting, and hardware in order. Jan uses the approved models and finish choices to coordinate what gets ordered and what each trade needs on site.
  4. Build against the approved drawings. Jan schedules trades, tracks materials, handles permits, walks the site, and checks the work. You receive one weekly update. If an unexpected condition comes up behind a wall, the person deciding how to handle it is the person who drew both rooms.
Kitchen with white raised-panel cabinets, granite counters, a dark wood island with a beverage refrigerator and a glass mosaic backsplash
Cedarbrush Kitchen, a Chateau Concepts project: the beverage refrigerator lives in the island, outside the cook’s path. The same thinking places a bar: drinks where guests can reach them without crossing the work zone.

Our kitchen remodeling in Highland Park and University Park includes design and construction. If you already have a builder, we also offer design-only engagements and hourly remodeling consulting for plans and selections your builder can use.

Frequently asked questions

Can you rebuild an existing wet bar while remodeling the kitchen?
Yes. We check the existing plumbing and appliance openings, then draw the new bar with the kitchen so both can share the appliance schedule and cabinetry order.
Can a bar have an ice maker without a sink?
Yes. A plumbed ice maker still needs a water supply and a drain. Those connections can affect whether the bar makes sense in the proposed location.
What can fit on a three-foot wall?
A compact beverage station can fit. Give the counter enough room to set down a glass and check the appliance opening, door swing, and storage before choosing cabinets.
Can the bar cabinets be different from the kitchen cabinets?
Yes. We can specify a darker finish or contrasting wood for the bar in the same cabinetry order. We review the finishes together before approval.
Can you order counters when you order the cabinetry?
You can select the stone during design. The fabricator templates the counters after the cabinets are installed, and template to installation typically takes 2–4 weeks.
Does a City of Dallas contractor registration cover University Park permits?
University Park has its own permit process. When Chateau Concepts is the general contractor, we file the project applications with University Park and show you the approved permit.
How do we get started with a kitchen and bar remodel?
Call 214-797-4657 or book a design consultation. We’ll meet at your house to discuss how you cook and entertain and look at where the bar could go.
Jan Revels, ASID Allied Professional Interior Designer
ASID, American Society of Interior Designers, Allied Professional Interior Designer · Chateau Concepts, Dallas

Jan has practiced interior design in Dallas since 1997 and founded Chateau Concepts in 2001. She holds a BFA in Interior Design from the University of North Texas. She designs and general-contracts residential and commercial projects across the Park Cities, Preston Hollow and North Dallas. Read her full profile →

Written and reviewed by Jan Revels before publication